Boiler replacement and upgrade
Our client operates a pharmaceutical packaging facility, which is temperature critical – the system must be maintained with a flow temperature of 80 degrees, around the clock.
Ellesmere installed the original boiler system 20 years ago and has provided service and maintenance support ever since. However, the system was nearing the end of its life cycle and with such high gas usage, achieving optimum fuel efficiency at the facility is vital.
Ellesmere was commissioned to carry out the installation of a new system using high efficiency, fully modulating Hamworthy Wessex Modumax MK3 boilers.
All works were successfully completed on time and within budget, with no disruption to the facility’s packaging processes. Our client has achieved impressive savings, with a 50{0a29a62f09d5c2728afe0de6873b75e5a76c9056e07e52a34f9bccd49a40d94c} reduction in their gas usage in the 1st month. This has significantly reduced their costs and CO2 emissions. They are delighted with the savings and with facilities operating worldwide, intend to roll out a boiler replacement programme across the Group.
If you’d like more information about how we can help you, give our team a call on 0161 799 7626 or get in touch here